Representative Engagements - Institutional/Educational/Hospital
- represented subcontractor with major overrun
claim before Pennsylvania Board of Claims involving the renovation of
the state capital complex. Represented major
contractor. Negotiated pass-through agreement.
- provided
advice concerning claims submitted by contractor in connection with
construction of University of Texas administrative facilities
- represented
Fortune 500 owner of a private corporate training center in defense of claims by
contractor and subcontractors in excess of $10 million relating to
construction of new buildings on private campus in New York, NY
- represented
prime contractor for plumbing and HVAC construction on initial phase
of expansion and additions to state capitol complex in prosecution of
claim for delay and disruption
- represented
regional general construction contractor in prosecution of claims for
changes and delay in construction of general mail facility in Red
Bank, NJ. Also represented contractor in suit for damages against
surety of terminated subcontractor.
- represented
prime contractor for electrical construction of expansion and
renovations to county hospital in terminating contract due to
extraordinary delay and in prosecution of claim for delay and
inefficiency
- represented national
construction management firm in defense of State Court litigation of
claims brought by the university relating to alleged defects in
construction of buildings at its campus in Philadelphia
- represented
central Pennsylvania general contractor of a high-rise retirement
facility in issues related to subsidence of structure
- represented
a charitable foundation in dealing with architect, contractors and
suppliers for its biomedical research facility in Boston, MA.
Developed project delivery system. Supervised all of owner's
representatives in bringing in project on budget and on time.
- represented
national general construction contractor for construction of new
student center/theater/activity center complex in Irvine, CA in
litigation relating to extra work, delays and disruptions; settled by
mediation
- drafted construction contracts
and construction manager's agreement for construction of new
vocational high school, Philadelphia school district's largest project
in 25 years. Also provided advice to district during construction
regarding claims and delays.