Montana Supreme Court Holds That a Waiver of Consequential Damages and a Partial Limitation of Liability in a Design Contract Are Not Contrary to Montana Law

Zirkelbach Constr., Inc. v. DOWL, LLC, 2017 Mont. Lexis 591 (Mont., Sept. 26, 2017)

Author: Emily D. Anderson

11/30/2017

Read the full post at Constructlaw

Montana Supreme Court Holds That a Waiver of Consequential Damages and a Partial Limitation of Liability in a Design Contract Are Not Contrary to Montana Law

In interpreting a state statute which makes contractual limitations on a party’s liability unenforceable in certain instances, the Supreme Court of Montana recently upheld the validity of a contract provision in a professional services agreement between a general contractor and a designer in which the parties waived consequential damages against each other and limited the liability of the designer to $50,000.00.