Federal Court Holds That, Under Louisiana Law, a Contractor Need Not Show a Total Work Stoppage to Recover Extended Home Office Overhead Under Eichleay

Team Contrs., L.L.C. v. Waypoint NOLA, L.L.C., No. 16-1131, 2017 U.S. Dist. LEXIS 162172 (E.D. La. Oct. 2, 2017)

Author: Jane Fox Lehman

12/07/2017

Read the full post at Constructlaw

Federal Court Holds That, Under Louisiana Law, a Contractor Need Not Show a Total Work Stoppage to Recover Extended Home Office Overhead Under Eichleay

Waypoint NOLA (Waypoint) was the owner of a hotel construction project in New Orleans (the Project).  Waypoint contracted with Team Contractors (Team) to serve as the Project general contractor and HC Architecture (HCA) to serve as the Project architect.  HCA, in turn, subcontracted with KLG to prepare the mechanical, electrical, and plumbing (MEP) plans.